Legislation Details

File #: 20-8418    Version: 3 Name: RES - nCino Contractor CO
Type: Resolution Status: First Reading
File created: 1/23/2024 In control: City Council
On agenda: 2/20/2024 Final action:
Title: Resolution Authorizing the City Manager to Execute a Change Order with T.A. Loving Company for the nCino Sports Complex (3CRPK1863) in an Amount Not to Exceed $751,000 [Budget Impact $751,000]
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Title

Resolution Authorizing the City Manager to Execute a Change Order with T.A. Loving Company for the nCino Sports Complex (3CRPK1863) in an Amount Not to Exceed $751,000 [Budget Impact $751,000]

 

Body

LEGISLATIVE INTENT/PURPOSE:

 

WHEREAS, this resolution authorizes the execution of a construction contract change order for the nCino Sports Complex project with T.A. Loving Company in the amount not to exceed of $ 751,000; and,

 

WHEREAS, the construction contract change order is needed for the installation of the engineered pile foundations for site lighting at the sports complex to address compaction of poor soils; and,

 

WHEREAS, this project will accommodate a diversity of programming, including but not limited to youth and adult soccer, lacrosse, football, rugby, and ultimate frisbee.

 

THEREFORE, BE IT RESOLVED:

 

THAT, the City Manager is authorized to execute a construction contract change order with T.A. Loving Company for the construction of the nCino Sports Complex Project, in an amount not to exceed of $751,000.00.