Title: Resolution Rejecting All Bids for the Hooker Road MUP (U-5534G), Hinton Avenue MUP (U-5534H), and Wrightsville Avenue/Greenville Avenue Intersection Improvements (U-5534C) Projects
Attachments: 1. Resolution - Bid Rejection - Hooker, Hinton, Wrightsville/Greenville
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
title
Resolution Rejecting All Bids for the Hooker Road MUP (U-5534G), Hinton Avenue MUP (U-5534H), and Wrightsville Avenue/Greenville Avenue Intersection Improvements (U-5534C) Projects

body
Department:
Engineering
Meeting Date:
8/5/2025
Contact Name:
Rachel McIntyre
Public Hearing:
No
Contact Phone:
910-765-0581
Advertising Date/Advertised By:
N/A
Attachments:
Attachment #1: Resolution - Bid Rejection

PURPOSE:
Attached for your consideration is a resolution to reject all bids for the Hooker Road Multi-Use Path (MUP) (U-5534G), Hinton Avenue MUP (U-5534H), and Wrightsville Avenue/Greenville Avenue Intersection Improvements (U-5534C) projects.

BACKGROUND:
The projects are federally funded through the Wilmington Urban Area Metropolitan Planning Organization ("WMPO") via the Surface Transportation Block Grant - Direct Attributable ("STBG-DA") program, passing through the NCDOT and requiring a 20% local match from the City. While these projects are individually funded, they are in close geographic proximity to each other and have been combined for the design and construction phases.

The City advertised the Hooker Road MUP (U-5534G) project, combined with the Hinton Avenue MUP (U-5534H) and Wrightsville Avenue/Greenville Avenue Intersection Improvements (U-5534C) projects, for bid on January 30, 2025. A bid opening was scheduled for March 25, 2025, but an insufficient number of bids was received to open, and the projects were re-bid. Bids were opened on April 3, 2025, and one proposal was received, which greatly exceeded the engineer's estimate and overall budget for the projects. On May 6, 2025, City Council rejected the bid.

The bid documents and cost estimate were revised, and the projects were re-advertised on June 3, 2025. Bids were opened on July 8, 2025, and three bids were received.

Two of the bids received used the incorrect proposal forms from the original advertisement, including the low bidder. It was discovered on July 11, 2025 that C...