Title: Resolution Awarding the Construction Contract for the Wrightsville Avenue Sidewalks and Roundabout Project to Chatham Civil Contracting, LLC of Pittsboro, NC in the Amount of $6,033,187
Attachments: 1. 20250520 Wrightsville Avenue SW & RAB - Construction Contract Award Resolution, 2. 20250520 Wrightsville Avenue SW & RAB - Certified Bid Tabulation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

 Resolution Awarding the Construction Contract for the Wrightsville Avenue Sidewalks and Roundabout Project to Chatham Civil Contracting, LLC of Pittsboro, NC in the Amount of $6,033,187

 

body

Department:

Engineering

Meeting Date:

5/20/2025

Contact Name:

Mike Naklicki

Public Hearing:

No

Contact Phone:

910-341-5897

Advertising Date/Advertised By:

N/A

Attachments: 

Attachment #1:  Resolution Awarding Contract Attachment #2:  Certified Bid Tabulation

 

PURPOSE: 

The purpose of this resolution is to authorize the City Manager to execute a contract with Chatham Civil Contracting, LLC (“Chatham”) in the amount of $6,033,187.04 for the construction of the Wrightsville Avenue Sidewalks and Roundabout Transportation Bond project (“Project”), 2TRST1566.

 

BACKGROUND:   

The Project is part of the City’s Transportation Bond program and involves construction of continuous sidewalk for approximately 2.6 miles on the north side of Wrightsville Avenue, from the intersection of Independence Boulevard and Wrightsville Avenue to the intersection of Hawthorne Drive and Wrightsville Avenue. Additionally, a single lane roundabout will be constructed at the intersection of Wallace Avenue and Wrightsville Avenue. Pedestrian signals, curb ramps, and crosswalks will be adjusted at the intersection of Wilshire Boulevard and Wrightsville Avenue and installed at the intersections of College Road and Wrightsville Avenue and Hawthorne Drive and Wrightsville Avenue to facilitate safer pedestrian crossings of these high traffic volume roadways.

 

The Project was competitively bid through the City’s Purchasing Department, with Chatham being the lowest responsible responsive bidder in the amount of $6,033,187.04.

 

budget

BUDGET IMPACT:  

$575,482 from Interest Earnings will be used to pay for the Project, with the remaining funding coming from the various Transportation Bond projects and the contingency funds within those projects. An accompanying ordinance lays out the various funding sources to be used.

 

recommendation

RECOMMENDATION / ACTION REQUESTED:

City staff recommends award of the construction contract.