PURPOSE:
The purpose of this resolution is to authorize the City Manager to enter an Interlocal Agreement (“ILA”) to establish a cost recovery agreement between the City and Cape Fear Public Utility Authority (“CFPUA”) for the Wisteria/Clearbrook Drainage Improvement Project Stage II (“Project”).
BACKGROUND:
The City plans to begin construction on the Project, including relocation of water and sewer line facilities in conflict with storm drainage pipes, which will be reimbursed by CFPUA. The direct costs for the construction of water and sewer line relocation within City right of ways shall not exceed $118,700 (which includes 10% contingency) without further authorization from CFPUA.
budget
BUDGET IMPACT:
CFPUA will reimburse the City an amount not to exceed $118,700 for direct costs of water and sewer line relocation. City funds are available in Stormwater Capital Projects fund for the Project.
recommendation
RECOMMENDATION / ACTION REQUESTED:
Staff recommend passage of this resolution.